The construction of 400 kV transmission line Jylkkä - Kukonkylä

Fingrid Oyj, Helsinki · HERRFORS NÄT-VERKKO OY AB, Pietarsaari

Kuvaus

Fingrid Oyj is requesting Tenders for the construction of two new parallel 400 kV transmission line with 110 kV circuits between Jylkkä and new Kukonkylä substation along with necessary modifications to the existing network. The lines are designed for their own, parallel-placed supports. The length of line route is app. 40 km The scope of work of the Tender will not be amended; however, the change will affect the payment responsibility between the Fingrid and the buyer towards the contractor. Part of the tender, the 110kV Circuit will be bought and paid by buyer instead of the Fingrid. The change will also affect the following three (3) items, to which modification and additional work will be needed 1) 400 kV/110 kV double circuit supports, foundations and earthings and 2) 110 kV double circuit supports, foundations and earthings and 3) already ordered option 1, Verkasalo wind farm connection

Sopimus ja tulokset

Sopimuskausi
1.1.2027–22.10.2027

Tulos 4.7.2025

  • LEONHARD WEISS OU · 4 000 000 €

CPV-luokitus

  • 45231400 Sähkölinjojen rakennustyöt (pääluokitus)

Ilmoitukset

  1. 26.11.2026 Sopimusmuutosilmoitus

Tiedot ovat julkisten hankintojen ilmoituskanava Hilmasta (hankintailmoitukset.fi). Tarkista hankinnan ehdot aina alkuperäisestä ilmoituksesta ja hankinta-asiakirjoista.